Breakers Resort Engine Room Renovation – Power Systems Analysis

This major renovation and expansion of the resort’s electrical infrastructure included new medium-voltage switchgear to serve the hotel, laundry, and central plant facilities.  Emerald worked directly with the electrical equipment manufacturer, electrical contractor, and utility provider to perform an arc flash analysis, protective device coordination study, and short-circuit analysis for the entire system.  All analyses were performed using SKM PowerTools software.

Project Details

PROJECT LOCATION

Palm Beach, FL

PROJECT COMPLETION

2017

PROJECT TYPE

Power Systems Analysis